August
2010–Present
Lufkin, TX
P Project Planner/
Scheduler (Southern Project Controls LLC.)
§
Site Project
Control Planner for Southern Project Controls LLC. (Lufkin Industries
Manufacturing Plant, & Montiff Chemical Plant ,Diboll, TX )
§
Responsible for
Construction and Turnaround Outage schedules updates and prepare weekly
reports on job status and progress. (Prepare CPM risk analysis and
assessment and coordinate bimonthly meetings to review analysis results and
resolutions.)
§
Prepare Curves
and Schedule analysis of Negative Progress Disciplines and provide
resolution and variables to retain schedule Completion within the budget
and baseline schedule deadlines.
§
Responsible for
maintaining daily verification on progress of project site as well as
provide Daily work schedules for Disciplines and projected work
Scope. As well as send daily reports to Senior Scheduler on success
or failures to meet the Scheduled Milestones. Work to resolve scheduling
issues for procured materials and Equipment delayed by manufacturing or
fabrication. Causing schedule conflict.
§
Report the
daily Checklist and Critical Path sub schedules to Project Control Center,
to Project Management Staff. ( Owners and Stake Holders )
§
Responsible for
Schedule Update meetings including, Construction, Testing and
Commissioning, Pre Operational Functions, including Scheduling Station
Valve Testing for Commissioning Group.
§
Responsible for
Coordinating Pipeline Construction and The Metering Contractor as Well as
the Compressor Station Contractor Integration to Tie ins and
completion for Commissioning.
August
2009–August
2010
Carmike Cinemas
(SR Assistant Manager)
Lufkin, TX
Maintained a stable crew of 25 personnel &
maintained concession at Theatre with 9 auditoriums and operation of the
nine simultaneously.
Responsible for Scheduling Movies & Maintaining
for Special Showings and Correct Show time of operation...Group and Class
Showings Also Live (Satellite) Opera Network Operation feed. Software for
Live Show.
Responsible for Maintaining Operational function and
inspection of the Theatre New Digital 3D Projector Equipment 9 Projecting
Equipment. 1 Million Dollars Equipment Costs.
Prepared New Movies, Received & Inventoried,
Built and Spliced movie reels as well as inspected maintenance on
operational equipment. Once finished showing, Prepared for Shipment (Older model and digital movies
valued at $25,000 - $75,000) Confirmed shipping and delivery to Movie Issue
and control Dept.
S Sept
2008—May 2009 Alliance
Engineering
Sterlington,
La.
P Project Planner/
Scheduler (Sterlington Compressor Station )
§
Site Project
Control Planner for a Gulf Crossing Project Engineering & Grassroots
Construction of New Compressor Station in Sterlington, LA through
Commissioning and Operational Schedules. $460 Million Cost
§
Responsible for
Construction schedule updates and prepare weekly reports on job status and
progress. (Prepare CPM risk analysis and assessment and coordinate
bimonthly meetings to review analysis results and resolutions.)
§
Prepare Curves
and Schedule analysis of Negative Progress Disciplines and provide
resolution and variables to retain schedule Completion within the budget
and baseline schedule deadlines.
§
Responsible for
maintaining daily verification on progress of project site as well as
provide Daily work schedules for Disciplines and projected work
Scope. As well as send daily reports to Senior Scheduler on success
or failures to meet the Scheduled Milestones. Work to resolve scheduling
issues for procured materials and Equipment delayed by manufacturing or
fabrication. Causing schedule conflict.
§
Report the
daily Checklist and Critical Path sub schedules to Project Control Center
at Paris Texas and Houston, to Project Management Staff. ( Owners and Stake
Holders )
§
Responsible for
Schedule Update meetings including, Construction, Testing and
Commissioning, Pre Operational Functions, including Scheduling Station
Valve Testing for Commissioning Group.
§
Responsible for
Coordinating Pipeline Construction and The Metering Contractor as Well as
the Compressor Station Contractor Integration to Tie ins and
completion for Commissioning.
§
|